RCC pipe culverts at Dumdumia, Rangamati

Ongoing

Two phases of reinforced concrete pipe culvert construction on a hill road at Dumdumia for the 34 Engineering Construction Brigade of the Bangladesh Army, a single vent culvert followed by a double vent culvert.

Project facts

Client
Bangladesh Army (34 Engineering Construction Brigade)
Location
Dumdumia, Rangamati
Contract value
BDT 11.0 M
Status
Ongoing

Sum of the 1st phase (BDT 4,460,000) and 2nd phase double vent culvert (BDT 6,535,000) contracts.

Project photographs

Scope

  • Hillside excavation and cutting for the culvert alignment
  • Reinforcement and concreting of the culvert base slab with site-mixed concrete
  • Laying of precast RCC pipe sections on the concrete bed, single vent in phase 1 and double vent in phase 2
  • Headwall and wing wall reinforcement with steel formwork
  • Brick aggregate sub-base spread and compacted between the culvert walls
  • Army engineering personnel inspect and measure the reinforcement before each pour